Haikou Employee Activity Center Project Reaches Major Construction Milestone

On January 23, an aerial view of the Haikou Employee Activity Center project was taken.Photo by reporter Kang Denlin

Haikou Daily News on January 23 (Reporter Wang Xunbo, Correspondent Yang Jing and Deng Yao) On the morning of January 23, as the last large parallelogram box girder was accurately hoisted into place, the main steel structure of the Haikou City Employee Activity Center project was capped. The project was completed by This comprehensively enters the secondary structure construction stage.

On the morning of that day, the reporter saw at the project site that the Haikou City Employee Activity Center project has a maximum of 5 floors after the roof is capped, and the large and small steel structures are closely connected, which is very spectacular. Construction workers are distributed at relevant work points of the steel structure frame and are busy in an orderly manner.

According to the person in charge of the Haikou Employee Activity Center project, the project will officially start construction in October 2022. The construction content includes a performance hall, a cinema, a model worker deeds hall, a badminton (table tennis) hall, a basketball (volleyball) hall, a swimming pool, and training classrooms. The activity room and other venue facilities are scheduled to be completed in June 2025.

Workers are working with a tower crane to lift the last box beam.Photo by reporter Kang Denlin

The project was designed by Cui Kai, an academician of the Chinese Academy of Engineering and a national engineering survey and design master. It is constructed using a large-span jump-layer diagonal grid steel inclined column system, which is shaped like an inverted pyramid and fully demonstrates the structural aesthetics.

According to reports, in view of the project’s large steel structure, tight construction period, complex structural form, many overweight and large special-shaped components, and high visual and quality requirements for the steel structure, the project team established progress, technology, and quality attack teams. Adhere to the “zoned staggered synchronous flow construction” and point-to-point dedicated personnel tracking and responsibility systems, adopt “a la carte” order processing and delivery, and BIM technology to deepen modeling, strictly control the progress of each process and the installation accuracy of steel inclined columns, 3 Approximately 10,000 tons of steel structure installation was completed in one month, pushing the project to be capped nine days ahead of schedule.

Currently, more than 300 workers are working on this project, and work will not stop during the Spring Festival. Subsequently, the number of construction workers will be adjusted according to project needs, and all efforts will be made to sprint towards various established nodes.

The Haikou Employee Activity Center project is located on the west side of Xingyang Avenue and south of Jiangdong Avenue in Jiangdong New District, Haikou. After completion, it will meet the diverse needs of employees for life and leisure through the composite sharing of functions and the use of shared and open spaces, and become an enriching employee An important carrier for the spiritual and cultural life of the masses and improving the quality of the workforce.

Original title: The capping of the main structure of the Haikou Employee Activity Center project is scheduled to be completed in June next year

Editor in charge: Wang Ping
2024-01-24 02:27:43
#capping #main #structure #Haikou #Employee #Activity #Center #project #scheduled #completed #June #yearNews #CenterNanhai #Net

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *