Construction Progress and Updates: December 23-29 at Gigante de Arroyito

Learn about the tasks carried out between December 23 and 29.

Since Sunday, November 12, our Gigante de Arroyito is under construction to expand its capacity and to remodel several sectors. With the aim of periodically providing information to rogue members and fans, we continue with weekly reports about how work at home is progressing.

The construction company EDECA, which is carrying out the work, provided the following detailed information about the tasks carried out between December 23 and 29.

CONSTRUCTION PROGRESS:
1.1 PREVIOUS STUDIES:
Surveys and topography tasks continue. The
architectural projects, structural calculations and other engineering.
1.2 DEMOLITIONS AND SOIL MOVEMENT TASKS:
All demolition and demolition tasks were 100% completed.
ground movement. Reconstruction of the breaks caused has begun
on site (walls and sidewalks).
1.3 PLAYING FIELD:
The drainage work of the playing field was 100% completed.
The 3-9 stone was collected, distributed and leveled as planned.
The distribution of the 30cm sand and peat mixture throughout the entire
of the land, and its profiling is being carried out at this time.
Sod laying is expected to begin next week.
1.4 CONCRETE STRUCTURES:
The execution of all the foundation beams on the four
sides of the stadium, and the precast slabs were assembled in their entirety. HE
They left the slabs on the drains on hold (in progress). work is being done
in the placement of mortars to join them, and the execution of partitions
perimeters.
1.5 STORM DRAINS:
The excavations for the drainage work continue, and the assembly of the
themselves. Once this installation is done, we proceed to place the piece
corresponding premolded.
1.6 TUNNEL:
The work of foundations, concrete partitions and masonry continues to
the closure of the new tunnel. The old stands that will remain are being conditioned
visible inside the tunnel.
1.7 MISCELLANEOUS:
The structure and fabric of the popular sector was sent to be galvanized for its
subsequent assembly.
The remodeling of the home locker room continues. The
masonry of the same and began with the installations. New ones were purchased
floors and coverings, and new furniture was designed.
1.8 IRRIGATION SYSTEM:
The assembly of this system began as planned.
1.9 FIRE NETWORK:
All of this material is under construction. Preparation began
ground to begin these tasks.
05.02 CARC – Weekly Report 231229
1.10 ELECTRICAL NETWORK:
The tasks to lower the electrical trays and eliminate the
interference with the tunnel. Electrical tasks continue for the facilities
of irrigation, fire, and tunnel lighting, with their respective panels.

PHOTOGRAPHIC DEVELOPMENT:

FINAL PROFILE OF SAND AND PEAT ON THE PLAYING FIELD

IRRIGATION INSTALLATION

EXECUTION OF PERIMETER PARTITIONS AND STORM DRAINS

EXIT TUNNEL – PREPARATION OF CONCRETE PARTITIONS

LOCKER ROOMS – FACILITIES

2023-12-29 16:41:58
#Work #continues #Giant #weeks #progress