New York transit officials announced that the Grand Canal Court basketball facility in lower Manhattan is scheduled to reopen by late November 2026. The site has been shuttered since 2022, when crews dismantled the original courts to construct a subterranean traction power substation designed to support the New York City Subway’s Eighth Avenue line.
Subterranean Electrical Facility Boosts Train Service Capacity
The capital project places the new electrical facility directly beneath the public recreation space at the intersection of Sixth Avenue, Canal Street, and Thompson Street. According to records from the Metropolitan Transportation Authority, the subterranean installation will supply traction power to A, C, and E trains running through the corridor. Transit planners expect the upgraded electrical infrastructure to boost power reliability and accommodate an increased service frequency of up to five additional trains per hour along the Eighth Avenue line.
Construction crews have maintained pedestrian pathways around the active work zone near the Sixth Avenue entrance of the Canal Street subway station throughout the project timeline. The restored public space will feature new basketball hoops, benches, drinking fountains, upgraded fencing, and modern lighting systems.
Project Costs Nearly Double Due to Site Conditions
State transportation records show that project costs have expanded significantly since initial planning began. The capital program budget for the Canal Street substation started at $45 million in 2014. By December 2025, updated capital plan documents listed the total project cost at $83.773 million, representing an increase of roughly 86 percent.
Metropolitan Transportation Authority officials attributed the cost growth to several complex field conditions. Unanticipated underground utility lines, coordination hurdles with outside municipal agencies, real estate complications, equipment procurement expenses, and rising labor and support costs drove the budget upward over the course of construction.
The scheduled completion date has also shifted multiple times. In December 2022, transit officials anticipated finishing the work by the end of 2024. A March 2023 document from Manhattan Community Board 2 subsequently projected that the surface park would reopen in the third quarter of 2024, with overall construction running through late 2025. On-site construction signage later pointed to an April 2026 completion window before transit and park agencies finalized the current late November 2026 reopening target.