FIFA Delegation to Visit Morocco for 2030 World Cup Venue Evaluation

The inspection delegation will visit Rabat, Casablanca, Tanger, Marrakech, Agadir and Fès starting November 28 to evaluate stadium progress, transport networks and hotel capacity, Maroc Diplomatique reported.

The visit follows similar FIFA missions in Portugal and Spain as the three co‑hosts enter a coordinated review period.

Fès funding gap

The Fès Sports Complex carries a total estimated cost of 4.34 billion dirhams, yet the 2027 draft finance bill allocates only 14 million dirhams in payment credits — roughly 0.3% of the project cost — according to an analysis of the PLF 2027 by Amouri Consulting published in L’Economiste.

The study, authored by Mohammed Amouri, parliamentary adviser for the CGEM group and vice‑president of the Finance Committee at the House of Councillors, finds the budget documents do not identify the financing circuit, the updated project cost or the disbursement schedule.

Contracts have been awarded: SGTM won a first lot covering structural works, metal framework, waterproofing and finishes for about 2.825 billion dirhams including tax, while two further lots for electrical installations and fluids are estimated at 1.52 billion dirhams. “The fact that contracts are described as ‘approved’ does not establish that funds are available or set payment deadlines,” the Amouri Consulting analysis says.

Regional disparity

At the Fès‑Meknès regional level, 2027 sports payment credits total 334 million dirhams. The new Meknès grand stadium alone accounts for 300 million, while Fès’s two projects — the Sports Complex and the reconstruction of Stade Hassan II — share 34 million (14 million and 20 million respectively). The regional investment note cites a January 2027 delivery target for Stade Hassan II, a date absent from budget documents.

Photo: Maroc Diplomatique

Nationally, the study lists 17 sports projects with a combined cost of 26.288 billion dirhams and 3.106 billion dirhams in 2027 payment credits. Nearly 75% of that envelope is concentrated in Casablanca‑Settat, Rabat‑Salé‑Kénitra and Tanger‑Tétouan‑Al Hoceïma. The Grand Stade Hassan II in Benslimane receives 889 million dirhams, the Prince Moulay Abdellah complex in Rabat 550 million, and the Grand Stade de Tanger 494 million, according to L'Economiste.

Economic stakes

Youth, Culture and Sports Minister Mohamed Mehdi Bensaid told the House of Councillors’ Education and Cultural Affairs Committee that World Cup‑linked investments should generate 840,000 jobs, with 52% in construction, La Nouvelle Tribune reported. Tourism targets aim for 26 million visitors by 2030, with tourism GDP projected at 134 billion dirhams at constant prices and receipts exceeding 156 billion dirhams, according to La Nouvelle Tribune.

Photo: Goal.com

Inspection tour begins November 28

The evaluation will measure the level of preparation of the candidate cities, their capacity to host sports delegations and supporters, and the fluidity of travel between the different competition sites.

Heritage argument

The evaluation will measure the level of preparation of the candidate cities, their capacity to host sports delegations and supporters, and the fluidity of travel between the different competition sites.

The Grand Stade Hassan II is the option the Kingdom will put forward to try to host the final, one of the most debated files for the 2030 edition.

Other cities and regions will be able to host the training camps of the selections, by making available training and accommodation facilities.