The Cost of Ambition: Ghent’s Rowing Tower Project Derailed
For the third year in a row, the international rowing community gathered at the Watersportbaan in Ghent for the Spring Regatta, facing a familiar, makeshift sight: a competition tower constructed from shipping containers. While more than 1,000 domestic and international athletes descended on the venue, the “hypermodern” facility promised to the city and its athletes remains a skeletal reminder of a project gone wrong.
What was intended to be a crown jewel for Belgian rowing has instead become a cautionary tale of infrastructure failure. The construction of the new competition tower Ghent project has officially derailed, with costs tripling, the contractor suspended, and the structural stability of the building now in question.
A Project in Freefall: Costs and Contractors
The financial trajectory of the Watersportbaan tower has shifted from a planned investment to a budgetary nightmare. According to city records and admissions from local officials, the projected cost of the tower has tripled since the initial planning phases in 2021. If the site can even be restarted, the price tag is now estimated at approximately €2.8 million.
The collapse of the project is not merely financial but operational. The contractor hired for the build has been put in default twice and has since been suspended. This administrative breakdown has pushed the original completion deadline of June 2026 into the realm of impossibility. City officials now warn that the project could face delays lasting months, or potentially years.
The political fallout has been immediate. During a recent session, city council members Bob Cammaert (N-VA) and Sven Taeldeman (Voor Gent) pressed the administration for answers. Bram Van Braeckevelt, the Alderman (schepen) for Sport, offered a blunt assessment of the situation: “Everything that could travel wrong in this dossier, has gone wrong.”
Stability Concerns and the Architectural Vision
Beyond the money and the deadlines, there is a more fundamental problem: the building itself may not be sound. Reports indicate that stability problems have emerged, leaving the structural integrity of the tower uncertain. This is a devastating blow to a project designed to be a “blikvanger”—a visual landmark—for the Ghent sporting landscape.

The tower was designed by FELT architecture & design, featuring a distinctive “stepped overhang” (getrapte overkraging) intended to provide optimal visibility for race officials and a striking modern silhouette. The goal was to replace a crumbling 1970s-era structure that lacked basic insulation, had unsafe stairs, and failed to meet any contemporary sporting standards.
The old tower was demolished in November 2023 to make way for this vision. However, the gap between the architectural renderings and the current reality on the ground has left the city without a permanent officiating hub.
The Sporting Impact: Rowing in the Interim
For the athletes, the administrative chaos translates to a lack of professional infrastructure. The Watersportbaan is a critical hub for Belgian rowing; historically, nearly three-quarters of Belgian rowing titles have emerged from Ghent-based clubs. To maintain this level of excellence, the city argued that the infrastructure needed to evolve.
However, the delay means that major events continue to rely on temporary solutions. Jonas Deconinck, an organizer for the Spring Regatta, had expressed hope that the new build would be finished before the start of the next season. Those hopes have since been characterized as “idle.”
To put this in perspective, here is how the current state of the facility compares to the original goals:
| Feature | Planned/Goal | Current Status (April 2026) |
|---|---|---|
| Completion Date | June 2026 | Totally unachievable; delayed months/years |
| Estimated Cost | ~€930,000 (2021 estimate) | ~€2.8 million |
| Tower Structure | Hypermodern FELT design | Suspended contractor; stability uncertain |
| Officiating Hub | Permanent high-tech tower | Temporary shipping containers |
Broader Infrastructure Context: The Dredging Success
not every aspect of the Watersportbaan transformation has been a failure. While the tower has stalled, the water itself has seen significant improvement. The rowing course, which had not been properly dredged since 1977, was a collection of silt and debris that left some edges as shallow as 60 centimeters.
Beginning in October 2022, the city undertook a massive dredging operation, removing 35,000 cubic meters of silt—the equivalent of 14 Olympic-sized swimming pools. The goal was to ensure a minimum depth of two meters across the entire course, allowing rowing shells to move faster and without obstruction. This phase of the project was intended to transform the venue into a true “top sport” accommodation.
The irony is that while the water is now optimized for elite performance, the officials overseeing those performances are still operating out of containers.
Accountability and the Path Forward
The failure of the tower project has sparked a debate about the management of public funds in Ghent. The city administration has admitted that the current state of the dossier is not how government money should be spent. Despite the suspension of the contractor and the stability warnings, Alderman Van Braeckevelt has stated that the city still wants to open the tower as quickly as possible.

The road to recovery is unclear. The city must now determine if the current structure can be salvaged or if the stability issues require a total rethink of the build. With the contractor suspended, finding a new partner who is willing to seize over a “derailed” project—and potentially inherit its structural flaws—will be a significant challenge.
For now, the rowing community must continue to adapt. The Watersportbaan remains a vital piece of Belgian sporting heritage, but its transition into the modern era has hit a wall of concrete and bureaucracy.
Next Checkpoint: The city of Ghent is expected to provide further updates on the potential restart of the construction site and the resolution of the contractor’s suspension. We will monitor official city council reports for any revised timelines.
Do you think the city should scrap the current design and start over, or is the FELT vision still worth the investment? Let us realize in the comments.